Intel Fab 42

Chandler, Arizona

Case Study: Download

PROJECT FACTS:

Name: Fab 42

Location: Chandler, AZ

Type: Semiconductor Wafer Fabrication

MAXIM FACTS:

Project Duration: 2011 to 2012

Total Contractors: 
25

Man Hours Worked: 
91,462

CRANE STATS:

Cranes On-Site:

11 Conventional Crawler Cranes

10 All Terrain/Hydraulic Trucks

11 Rough Terrain Cranes

Total: 32

 

The Project

Located in Chandler, Arizona, Intel Fab 42 is one of the most advanced high volume semiconductor factories in the world. Fab 42 required over 24,000 tons of steel rebar, 21,000 tons of structural steel and the excavation of 875,000 cubic yards of dirt. The total project cost was $5.0 billion.

The scope and scale of this project required the comprehensive lift solutions that only a company with Maxim’s resources can provide. This included over 30 operated and maintained cranes of various types and sizes. A major element of the project was the use of a 3,200 metric ton crane, one of the largest in the world. In addition, Maxim provided project planning, project engineering, and industry leading safety practices for the duration of the project.

The Result

Over 90,000 hours of work completed without a major safety incident.

Maxim Crane Works

Join the Talent Community

Tell us where you want to work and what you do. We will send job alerts, hiring updates, and employee stories that match your interests.

By submitting this form, you agree to receive email communications from Maxim Crane regarding job opportunities, career openings, and company updates. You can unsubscribe at any time.

Work authorization: Maxim Crane Works does not provide visa sponsorship. Applicants must be authorized to work in the United States.